|
| HoldFast’s
New Anti-Trespass Guards Enter Network Service
November
2005
The first commercial installation of HoldFast’s new Anti-Trespass
Guards was heralded a success by all involved. The Guards were
installed alongside the HoldFast crossing replacement at Allington,
near Grantham, as part of the greater Allington Chord line project
undertaken by Carillion.
Three night time possessions were allocated to install the crossing
platform and adjacent Guards. Three shifts is an unusually long allocation
for HoldFast crossing installations.
However, there was significant preparation work required because of
the poor condition of the road approaches necessitating the excavation
and removal of the base and sub base around the crossing and new PVC
angle edge beams, also supplied by HoldFast.
Fifth Rail UK Limited, approved Network Rail contractors with 13 Link-Up
approvals, were HoldFast’s sub-contractors for the complete installation
process. The project was undertaken by Fifth Rail Manager, Roger Aubrey,
and a team of four PTS supplemented by a machine driver and chainsaw
operative.
Aubrey explains: “This job required more preparation work
than we normally encounter. If Bomac edge beams are already in place
it makes the installation of a HoldFast system even easier as there
is no requirement to cut back the tarmac or take the edge beams out.
“Such is the design of HoldFast panels, they locate precisely
on the Bomac edge beams to create a very stable platform. Nonetheless,
despite the added challenges, it proved to be another straightforward
installation, as HoldFast installations tend to be.”
HoldFast delivered direct to site on the afternoon preceding the first
closure. All plant, comprising a cement mixer, telehandler and mini
digger were hired locally. The new asphalt applied to the road approaches
and white lining was carried out by a division of Carillion.
HoldFast’s Anti-Trespass Guards proved simple and effective to
install. They are held down in position with metal ‘U’ shaped
spikes hammered into the ballast. Where certain panels needed to be
trimmed to size to fit (in the 6’ area), an experienced chainsaw
operative simply cut to size and fresh holes were drilled through the
panels on site.
HoldFast’s Managing Director, Peter Coates Smith, is delighted
to see their latest product take to the Network and adds: “We
already knew our Guards are safer and far more durable than the wooden
alternatives that rarely survive removal and replacement for tamping
without breaking up.
“Allington has now proven how easy they are to install. Of our
recent orders, most now include new Anti-Trespass Guards as part of
the long term crossing refurbishment solution.”
|
|

HoldFast's
Anti-Trespass and Cattle Guards installed successfully at Allington,
on the Carillion Greater Allington Chord Line project.

The newer
and more durable HoldFast Anti-Trespass and Cattle Guards replace more
traditional wooden and concrete guards.
The HoldFast
guards fit easily with the existing level crossing.
|